Project description: A project to construct a 4 megawatt solar plant in Uganda for the New and Renewable Energy Authority - Ministry of Electricity and Renewable Energy.

Project main data:

  • Total power: 4 megawatts.
  • Beginning of the contractual period: 12/2/2019
  • The installation work started on the site on 10/5/2021
  • Planned completion of installation: on 10/15/2021.